13.01 Purpose
This Article establishes the methods for implementation of these regulations. These provisions include procedures for reviewing specific uses within certain zoning districts; amending Zoning Regulations; and the variance process.
13.02 Zoning Enforcement Officer
- A.
Role Filled by Zoning Enforcement Officer
The role of the Zoning Enforcement Officer shall be filled by the Douglas County Zoning Coordinator. The term “administrative official” as referenced in this article shall mean the Douglas County Zoning Coordinator or designee.
- B.
Powers and Duties
The Zoning Coordinator shall exercise the following powers and duties:
- 1.
All enforcement powers, including but not limited to the investigation of complaints of zoning violations, issuance of notices to violators, and the preparation and submission to the County Attorney of reports of those zoning violations which continue unabated after exhaustion of reasonable administrative remedies toward their abatement, for such legal action as the facts of each report may require.
- 2.
Determine the use type for any use.
- 3.
In all cases in which the county commences court action, shall cooperate with the county attorney in investigations as required.
- 4.
Attend meetings of the Planning Commission and the Board of Adjustment, shall investigate and review all applications and cases presented, and shall advise on those applications and cases.
- 1.
13.03 Site Plan Review Procedure
- A.
Purpose
The Site Plan Review Procedure provides for the administrative review, in addition to plan review required by other sections of these regulations, of projects that have potentially significant effects on traffic circulation or a significant effect on land uses in adjacent neighborhoods. The procedure provides for review and evaluation of site development features and possible mitigation of unfavorable effects on surrounding properties.
- B.
Administration
The Zoning Coordinator shall review, evaluate, and act on all site plans submitted pursuant to this procedure. Site plan actions of the Zoning Coordinator related to enforcement may be appealed to the Board of Adjustment.
- C.
Uses Requiring Site Plan Review
Table 4.1. Permitted Uses by Zone District, identifies uses that are required to follow the Site Plan review procedure prior to the issuance of a building permit, unless they are otherwise subject to a Special Use Permit procedure for specific zoning districts. Permitted uses that are required to follow the Site Plan review procedure are noted in Table 4.1 with an asterisk.
- D.
Application Requirements
An application for a Site Plan Review may be filed by the owner(s) of a property or the owners' authorized agent with the Zoning Enforcement Officer. The application shall include the following information:
- 1.
Name and address of the applicant.
- 2.
Owner, address, and legal description of the property.
- 3.
A description of the nature and operating characteristics of the proposed use.
- 4.
A site plan, drawn to a scale sufficient to permit adequate review and dimensioned as necessary, showing the following information:
- a.
The date, scale, north point, title, name of owner, and name of person preparing the site plan.
- b.
The location and dimensions of boundary lines, easements, and required yards and setbacks of existing and proposed buildings and site improvements.
- c.
The location, size, and use of proposed and existing structures on the site.
- d.
The location of all proposed site improvements, including parking and loading areas, pedestrian and vehicular access, sewers, sidewalks, utilities, service areas, fencing, screening, signs, landscaping, and lighting.
- e.
Natural features assessment, as defined in these regulations and the Comprehensive Plan.
- f.
Location of any major site feature, including drainage and contours at no greater than five foot intervals.
- g.
Any other information that may be required for review by the Zoning Coordinator.
- a.
- 1.
- E.
Administrative Action and Appeal
The Zoning Coordinator will generally act upon each complete application within ten working days of filing unless the applicant is notified that additional time will be required. An applicant may appeal a zoning determination made as part of the site plan review to the Board of Adjustment.
- F.
Review and Evaluation
- 1.
The Zoning Coordinator shall review and approve the site plan based on the criteria established in Table 13.1 and conformance with applicable standards in this regulation.
- 2.
The Zoning Coordinator shall make the following findings before approval of the site plan:
- a.
The proposed development, together with any necessary modifications, is compatible with the criteria established in Table 13.1.
- b.
Any required modifications to the site plan are reasonable and are at least the minimum necessary to minimize potentially unfavorable effects.
- c.
The site plan conforms to these regulations and any other applicable County regulations.
- a.
- 1.
- G.
Term and Modification of Approval
- 1.
A site plan approval shall become void two years after the date of approval, unless the applicant receives a building permit and diligently carries out development prior to the expiration of this period.
- 2.
The Zoning Coordinator may approve an application to modify a previously approved site plan if it is determined that the modification does not affect findings related to the criteria set forth in Table 13.1.
- 3.
The Zoning Coordinator may revoke a site plan approval if it is determined that the development is not complying with the terms and conditions of the approval. Such revocation may be appealed to the Board of Adjustment.
- 1.
- H.
Approval to Run with Land
An approval pursuant to this article shall run with the land unless an expiration date of such approval is specified at the time of approval.
13.04 Special Use Permit Procedures
- A.
Purpose
To provide for public review and discretionary County Board approval for uses within zoning districts which have unusual site development or operating characteristics that could adversely affect surrounding properties.
- B.
Administration
The Planning Commission shall review and evaluate each application and transmit its recommendation to the County Board. The County Board shall review, evaluate, and act upon all applications submitted pursuant to this procedure.
- C.
Application Requirements
An application for a Special Use Permit may be filed by the owner(s) of a property or the owners' authorized agent with the Zoning Coordinator. The application shall include the following information:
- 1.
Name and address of the applicant.
- 2.
Owner, address and legal description of the property.
- 3.
A description of the nature and operating characteristics of the proposed use.
- 4.
Any graphic information, including site plans, elevations, or other drawings, necessary to describe the proposed use to approving agencies.
- 5.
List of surrounding landowners within 1/2 mile of subject property.
TABLE 13.1 – CRITERIA FOR SITE PLAN REVIEW AND SPECIAL USE PERMITS APPLICATION TO CRITERIA Site Plan Review Special Use Permit Land Use Compatibility Development Density Site Area per unit should be similar to surrounding uses if not separated by major natural or artificial features X Height and Scale Height and Bulk Development should minimize differences in height and building size from surrounding structures. Differences should be justified by urban design considerations. X X Setbacks Development should respect pre-existing setbacks in surrounding area. Variations should be justified by site or operating characteristics. X X Building Coverage Building coverage should be similar to that of surrounding development if possible. Higher coverage should be mitigated by landscaping or site amenities. X X Site Development Frontage Project frontage along a street should be similar to lot width. X X Parking and Internal Circulation Parking should serve all structures with minimal conflicts between pedestrians and vehicles. X X All structures must be accessible to public safety vehicles. X X Development must have access to adjacent public streets and ways. Internal circulation should minimize conflicts and congestion at public access points. X X Landscaping Landscaping should be integral to the development, providing street landscaping, breaks in uninterrupted paved areas, and buffering where required by surrounding land uses. Parts of site with sensitive environmental features or natural drainage ways shall be preserved, consistent with the conservation design regulations. X X Building Design Architectural design and building materials should be compatible with surrounding areas or highly visible locations. X Operating Characteristics Traffic Capacity County Engineer review required. Project should not reduce the existing level of traffic service on adjacent streets. Compensating improvements will be required to mitigate impact on street system operations. X X External Traffic Effects Project design should direct non-residential traffic away from residential areas. X X County Engineer review required. Operating Hours Projects with long operating hours must minimize effects on surrounding residential areas. X X Outside Storage Outside storage areas must be screened from surrounding streets and less intensive land uses. X X Public Facilities Sanitary Waste Disposal Developments within 500 feet of a municipal sanitary sewer should connect to sewer system. Individual disposal systems, if permitted, shall not adversely affect public health, safety, or welfare. X X Sanitary sewer must have adequate capacity to serve development. X X Storm Water Management Development should handle storm water adequately to prevent overloading of public storm water management system and such that there is no net increase in runoff from existing (pre-development) conditions. X X Development should not inhibit development of other properties. X X Development should not increase probability of erosion, flooding, landslides, or other run-off related effects. X X Storm water Best Management Practices, including the use of LID techniques, are required. X X Utilities Project must be served by utilities. Verify utilities to serve the development. X X Comprehensive Plan Projects should be consistent with the comprehensive development plan of Douglas County. X
- 1.
- D.
Approval Process
- 1.
The Planning Commission, following proper notice, shall hold a public hearing on each Special Use Permit (SUP) application and, following such public hearing, shall recommend action to the County Board. Such recommendation by the Planning Commission shall include the necessary findings of fact as required per Nebraska Revised Statute Section 23-114.01(6).
- 2.
The County Board, after publication and public hearing, shall act on the Special Use Permit. If the Planning Commission recommends denial of the Special Use Permit, a majority plus one of the County Board is required for approval. The County Board may apply any additional reasonable conditions to the approval of the SUP.
- 1.
- E.
Criteria for Review
The Planning Commission and the County Board shall review and approve the site plan based on the criteria established in Table 13.1 and conformance with the applicable regulations in this regulation.
- F.
Scope of Approval
The County Board may, at its discretion, apply a special use permit to a specific owner or applicant and may place a beginning and end date on a special use permit. The County Board may establish special site development or operational regulations as a condition of a special use permit.
- G.
Lapse and Revocation of Permit
- 1.
A special use permit shall become void two years after its effective date if the applicant has not carried out development or occupancy during that period. Such determination to be made by the Zoning Administrator.
- 2.
The County Board may revoke a special use permit should the operation of the subject to such permit violate the conditions under which the permit was granted.
- 1.
- H.
Previously Approved Permits
Any conditional or special use approved under regulations in effect before the effective date of this Regulation shall be considered to have a valid special use permit; subject to requirements imposed at the time of the original conditional or special use approval.
- I.
Required Notice and Publication
Prior to consideration of a special use permit, notice of public hearings shall be provided as follows:
- 1.
Publication: At least ten days before the date of hearing the Zoning Coordinator shall have published in the official County publication, notice of the time, place and subject matter of such hearing.
- 2.
Notice: A notice shall be posted in a conspicuous place on or near the property upon which action is pending. Such posted notice shall be so placed upon such premises that is easily visible from a public right-of-way and shall be so posted at least ten days before the date of such hearing. It shall be unlawful for any person to move, displace, remove, mutilate, destroy or change such posted notice prior to such hearing.
- 3.
Notice shall be provided to property owners within a half (1/2) mile (2640 feet) of subject property. Should adjoining property be owned by the applicant, a half (1/2) mile (2640 feet) shall be measured starting from the periphery of the applicant’s property.
- 4.
Notification of adjacent jurisdictions shall be pursuant to Nebraska Revised Statute section 23-164.
- 5.
These notification requirements will generally apply to all applications heard by the Planning Commission that involve a specific parcel of land.
- 1.
- J.
Timing Between Applications
If the Planning Commission recommends denial of an application, a new application for the same use on the same property must wait at least 180 days from the date of the Planning Commission denial date before re-filing with the Planning Department. An applicant filing a new application for the same use on the same property must show in that application substantive changes from the application that was previously denied. The determination of a substantive change will be made by staff. An application for a different use on the same property is not subject to this time restriction.
13.05 Amendment Procedures
- A.
Purpose
To describe the methods by which changes may be made in the text of the zoning regulations (text amendment) and/ or the official boundaries of zoning districts (rezoning).
- B.
Initiation of Amendments
- 1.
Text amendments may be initiated by the Planning Commission or County Board, staff, or a County property owner.
- 2.
Rezoning may be initiated by a County property owner, Planning Commission, County Board, or staff.
- 1.
- C.
Rezoning Application Requirements
An application and procedure sheet for a rezoning shall be obtained from the Zoning Coordinator.
- D.
Amendment Process
- 1.
The Planning Commission, following notice as indicated in this article, shall hold a public hearing on each proposed text amendment or rezoning and, following such public hearing, shall submit this recommendation to the County Board.
- 2.
The County Board, after publication and public hearing, shall act on the proposed amendment: If the Planning Commission recommends denial of the amendment, a majority plus one of the County Board is required for approval.
- 1.
- E.
Required Notice and Publication
Prior to consideration of amending, supplementing, changing, modifying, or repealing this regulation by the County Board, notice of public hearings shall be provided as follows:
- 1.
Publication: At least ten days before the date of hearing the Zoning Coordinator shall have published in the official County publication, notice of the time, place and subject matter of such hearing.
- 2.
Notice: A notice shall be posted in a conspicuous place on or near the property upon which action is pending. Such posted notice shall be so placed upon such premises that is easily visible from a public right-of-way and shall be so posted at least ten days before the date of such hearing. It shall be unlawful for any person to move, displace, remove, mutilate, destroy or change such posted notice prior to such hearing.
- 3.
Notice shall be provided to property owners within a half (1/2) mile (2640 feet) of subject property. Should adjoining property be owned by the applicant, a half (1/2) mile (2640 feet) shall be measured starting from the periphery of the applicant’s property.
- 4.
Notification of adjacent jurisdictions shall be pursuant to Nebraska Revised Statute section 23-164.
- 5.
These notification requirements will generally apply to all applications heard by the Planning Commission that involve a specific parcel of land.
- 1.
13.06 Building Permits and Certificates of Zoning Compliance
- A.
Administration and Enforcement
- 1.
The Zoning Coordinator shall administer and enforce this regulation. The County Board may direct other persons to assist.
- 2.
If the Zoning Coordinator shall find that any of the provisions of this regulation are being violated, he/she shall notify in writing the property owner of such violations, indicating the nature of the violation and ordering the action necessary to correct it. The Zoning Coordinator shall order discontinuance of illegal use of land, buildings, or structures; removal of illegal buildings or structures or of illegal additions, alterations, or structural changes;
discontinuance of any illegal work being done; or shall take any other action authorized by this regulation to ensure compliance with or to prevent violation of its provisions.
- 1.
- B.
Building Permits Required
No building or other structure shall be erected, moved, added to, or structurally altered without a permit therefore, issued by the relevant County official. No building permit shall be issued except if it is conformity with the provisions of this regulation, unless a written order from the Board of Adjustment in the form of an administrative review, special exception, or variance as provided by this regulation has been obtained.
- C.
Application for Building Permit
- 1.
All applications for building permits shall follow the established County building permit process, including but not limited to plans drawn to scale, showing the actual dimensions and shape of the lot to be built upon; the exact sizes and locations on the lot of buildings already existing, if any; and the location and dimensions of the proposed building or alteration. The application shall include such other information as may be required by the relevant County official.
- 1.
- D.
Expiration of Building Permit
- 1.
If the work described in any building permit has not begun within 180 days from the date of issuance thereof, said permit shall expire; it shall be cancelled by the Chief Building Inspector (CBI); and written notice thereof shall be given to the persons affected.
- 2.
If the work described in any building permit has not been substantially completed within two years of the date of issuance thereof, said permit shall expire and be cancelled by the CBI, and written notice thereof shall be given to the persons affected, together with notice that further work as described in the cancelled permit shall not proceed unless and until a new building permit has been obtained.
- 3.
The CBI may authorize in writing, one or more extensions of time, for periods, not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.
- 1.
- E.
Construction and Use to be as provided in Applications, Plans, Permits, and Certificates of Zoning Compliance
Building permits issued on the basis of plans and applications approved by the CBI authorize only the use, arrangement, and construction set forth in such approved plans and applications, and no other use, arrangement, or construction. Use, arrangement, or construction at variance with that authorized shall be deemed a violation of this regulation.
13.07 Schedule of Fees, Charges, and Expenses
- A.
The County Board shall establish a schedule of fees, charges, and expenses and a collection procedure for building permits, appeals, and other matters pertaining to this regulation.
- B.
The schedule of fees shall be available in the office of the CBI, and may be altered or amended only by the County Board, except that the Zoning Coordinator shall have the authority to process a refund for a collected fee.
- C.
Until all applicable fees, charges, and expenses have been paid in full, no action shall be taken on any application or appeal.
- D.
Required fees shall be quadrupled if construction has commenced prior to obtaining required permits.
13.08 Board of Adjustment
- A.
Establishment and Procedure
- 1.
A Board of Adjustment is hereby established by the County Board of Commissioners.
- 2.
Appeals shall be made to the Board of Adjustment through the office of Environmental Services on written forms as provided by the Office. Application fee is as established by the County.
- 1.
- B.
Conformance with State Statute
In addition to this section, the requirements of Nebraska Revised Statute sections 23-168.01 and sequence shall be followed.
- C.
Proceedings of the Board of Adjustment
The Board of Adjustment shall adopt rules necessary to the conduct of its affairs and in keeping with the provisions of this regulation and state statute. Meetings shall be held at the call of the Chairman, and at such other times as the Board may determine. Such chairman, or, in his/her absence, the acting chairman, may administer oaths and compel the attendance of witnesses. All meetings and records shall be open to the public. The board shall keep minutes of its proceedings, showing the vote of each member upon each question, or, if absent or failing to vote, indicating such fact.
13.09 Powers and Duties of the Board of Adjustment
The Board of Adjustment shall have only the following powers and duties:
The Board of Adjustment as established by the County Board shall have only the following powers, as described in Nebraska Revised Statute section 23-168.03:
- A.
To hear and decide appeals when it is alleged there is error in any order, requirement, decision, or determination made by an administrative official or agency based on or made in the enforcement of this zoning regulation or any regulation relating to the location or soundness of structures, except that the authority to hear and decide appeals shall not apply to decisions regarding special use permits granted by the County Board.
- B.
To hear and decide, in accordance with the provisions of this zoning regulation, requests for interpretation of any map; and
- C.
When by reason of exceptional narrowness, shallowness, or shape of a specific piece of property at the time of the enactment of this zoning regulation, or by reason of exceptional topographic conditions or other extraordinary and exceptional situation or condition of such piece of property, the strict application of this zoning regulation and state statute would result in peculiar and exceptional practical difficulties to, or exceptional and undue hardships upon the owner of such property, to authorize, upon an appeal relating to the property, a variance from such strict application so as to relieve such difficulties or hardship, if such relief may be granted without substantial detriment to the public good and without substantially impairing the intent and purpose of this zoning regulation.
- D.
Notice of public hearing shall be given as per the following procedures:
- 1.
Publication: At least ten days before the date of hearing the Zoning Coordinator shall have published in the official County publication, notice of the time, place and subject matter of such hearing.
- 2.
Notice: A notice shall be posted in a conspicuous place on or near the property upon which action is pending. Such posted notice shall be so placed upon such premises that it is easily visible from a public right-of-way and shall be so posted at least ten days before the date of such hearing. It shall be unlawful for any person to move, displace, remove, mutilate, destroy or change such posted notice prior to such hearing.
- 3.
Notice shall be provided to property owners within a quarter (1/4) mile (1320 feet) of the subject property. Should adjoining property be owned by the applicant, a quarter (1/4) mile (1320 feet) shall be measured starting from the periphery of the applicant’s property.
- 4.
The Board of Adjustment shall make findings of fact per Nebraska Revised Statute section 23-168.03 and this article.
- 1.
- E.
The board shall set out findings of fact based on evidence and testimony that the following conditions exist or would result:
- 1.
The strict application of the zoning regulation would produce undue hardship;
- 2.
Such hardship is not shared generally by other properties in the same zoning district and the same vicinity;
- 3.
The authorization of such variance will not be of substantial detriment to adjacent property and the character of the district will not be changed by the granting of the variance; and,
- 4.
The granting of such variance is based upon reasons of demonstrable and exceptional hardship as distinguished from variations of the regulations for the purpose of convenience, profit or caprice.
No variance shall be authorized unless the Board Adjustment finds that the condition or situation of the property concerned or the intended use of the property is not of so general or recurring a nature as to make reasonably practicable the formulation of a general regulation to be adopted as an amendment to the regulations.
- 1.
- F.
Conditions for Grant of Variance
- 1.
In granting any variance, the Board of Adjustment may prescribe appropriate conditions and safeguards in conformity with this regulation. Violation of such conditions and safeguards, when made a part of the terms under which the variance is granted, shall be deemed a violation of this regulation.
- 2.
Under no circumstances shall the Board of Adjustment grant a variance to allow a use not permissible under the terms of this regulation in the district involved, or any use expressly or by implication prohibited by the terms of this regulation in said district.
- 3.
No non-conforming use of neighboring lands, structures, or buildings in the same district and no permitted or non-conforming use of lands, structures, or buildings in other districts shall be considered grounds for the issuance of a variance.
- 1.
- G.
Board has Powers of Administrative Official on Appeals; Reversing Decisions of Administrative Official
- 1.
The concurring vote of four members of the Board shall be necessary to reverse any order, requirements, decision, or determination of the Zoning Coordinator, or to decide in favor of the applicant on any matter upon which it is required to pass under this regulation, or to effect any variation in the application of this regulation.
- 1.
13.10 Appeals from the Board of Adjustment
Any person or persons, or any board, taxpayer, department, board or bureau of the county aggrieved by any decision of the Board of Adjustment may seek review of such decision by the District Court for the County in the manner provided by the laws of the State and particularly by Neb. Rev. Stat. 23-168.04, and amendments thereto.
13.11 Severability Clause
Should any section or provision of this regulation be declared by the courts to be unconstitutional or invalid, such decision shall not affect the validity of the regulation as a whole, or any part thereof other than the part so declared to be unconstitutional or invalid.
13.12 Penalties for Violation
Any person who violates any of the prohibitions or provisions of any Article or Section of this Regulation shall be deemed guilty of a violation. Unless otherwise specified in the particular article or section for which the person stands convicted of violating, the penalty for such violation shall be a Class III misdemeanor. Every Twenty-four (24) hours in which a violation continues shall be considered a separate and distinct violation. (Ref. 23-114.05 RS Neb.)
13.13 Regulation of Conflicting Regulations
This chapter is not meant to repeal or interfere with enforcement of other sections of these Douglas County Zoning Regulations. In cases of conflicts between Douglas County, State or Federal Regulations, the more restrictive regulations shall apply.